Friday, March 28, 2008

Never ending inspections

It seems we are in a state of never ending inspections. We were granted our plumbing and electrical permits weeks ago, but the HVAC inspector has been slow to show up on site and has made the HVAC subs changes things twice already. I am really hoping we got our HVAC sticker today. IF we did, the GC can call for the framing inspection on Monday.

We are still a week out on getting in the rest of our siding from Nichiha and the garage floor was supposed to be poured Thursday or Friday, but so far, no floor. We are waiting on the stone, which needed to be special ordered. The garage doors haven't been stained yet, but after the garage floor has been poured and the dry wallers are done, they will be installed and stained on site.

This is a very frustrating stage, but hopefully, when we come out the other end, things will really start moving again.