This may have been one of the most encouraging construction days so far. The cabinet guys were finishing up the remainder of the cabinets and were down to affixing the cabinet knobs and pulls. The drywallers delivered scaffolding so the painters could stain the beams in the master bedroom and living room. Paint was also going up in the master. Draining pipes were installed from our down spouts to the lake. Hopefully this will help with erosion and our wall (which was beginning to wash away!) The tile installers showed up but the plumbing for the clawfoot wasn't in, so they left. However, that afternoon, the plumber showed up with my clawfoot tub (yeah! I was wondering if that had really arrived) and was adding the supply and drain lines for that. The tile guys SHOULD be back tomorrow to start on the master. The only disappointment was that the granite/soapstone installer was a no show. We have rescheduled for tomorrow. I'll snap some pictures of the progress then.